Planning Process Schedule
 
March 2007   Council Approval of Processing Agreement Amendment
April 2007   Submittal of Draft Specific Plan to City by McGrath Properties
June 2007   City Releases Citywide Traffic Model for Use in EIR
June 2007   Submittal of Draft Development Agreement to City by McGrath Properties
August 2007   Completion of Administrative Draft EIR
October 2007   Distribution of Draft EIR and Draft Specific Plan for public review
October 2007   Joint City Council/Planning Commission Study Session on Specific Plan
December 2007   Public Review Period Closes for Draft EIR
February 2008   Final EIR completed
March 2008   Planning Commission Hearing on Specific Plan, Development Agreement, General Plan Amendment and Rezoning
April 2008   City Council Hearing on Specific Plan, Development Agreement, General Plan Amendment and Rezoning
May 2008   LAFCO Application Filed for Annexation
August 2008   LAFCO Public Hearing
August 2008   LAFCO Issues Certificate of Completion

Note: LAFCO time frame is "best case"; variables include: (1) timing of a Master Tax Sharing Agreement between City and County, (2) LAFCO finding that City has adequate water and sewer capacity to serve Town Center annexation